Performance specification
- Track renewal track 243 (total conversion length: 580 m)
- Track renewal track 244 (total conversion length: 470 m)
- Track renewal track 245 (total conversion length: 900 m)
- Track renewal track 246 (total conversion length: 929 m)
- Track renewal track 247 (total conversion length: 909 m)
Construction procedure
- Long rails removed and stored outside the construction site
- Dismantling and removal of the existing track grid
- Old track bedding removed
- Basic ballast, laid as laying formation level using laser-controlled grader
- Track extension in individual materials
- Plugging and welding
- Track bed renewal
Special features
- All track construction work was carried out using the conventional track renewal method