Performance specification

  • Track renewal track 243 (total conversion length: 580 m)
  • Track renewal track 244 (total conversion length: 470 m)
  • Track renewal track 245 (total conversion length: 900 m)
  • Track renewal track 246 (total conversion length: 929 m)
  • Track renewal track 247 (total conversion length: 909 m)
Construction procedure
  • Long rails removed and stored outside the construction site
  • Dismantling and removal of the existing track grid
  • Old track bedding removed
  • Basic ballast, laid as laying formation level using laser-controlled grader
  • Track extension in individual materials
  • Plugging and welding
  • Track bed renewal
Special features
  • All track construction work was carried out using the conventional track renewal method